New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Scheduling Professional PMI-SP Question # 78 Topic 8 Discussion

PMI Scheduling Professional PMI-SP Question # 78 Topic 8 Discussion

PMI-SP Exam Topic 8 Question 78 Discussion:
Question #: 78
Topic #: 8

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?


A.

PERT


B.

Monte Carlo


C.

PMIS


D.

GERT


Get Premium PMI-SP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.