Question #: 77
Topic #: 8

Robert is the project manager for his organization. Management has asked Robert to provide them with the metric he uses to measure deliverables status, costs incurred, and especially how he measures the schedule progress for schedule adherence. What project component could Robert provide for management?


A.

Milestone list


B.

Cost management and the project schedule


C.

Work performance measurements


D.

Project management plan