Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Office Certified Professional PMI-PMOCP Question # 27 Topic 3 Discussion

PMI Project Management Office Certified Professional PMI-PMOCP Question # 27 Topic 3 Discussion

PMI-PMOCP Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

A PMO professional for an engineering company was contacted by a newly hired project manager who wanted to submit an urgent change request to reset the baseline for the project schedule. The project manager did not understand the process for submitting such a request. Because this project is critical for the company, any delays might put the project at risk.

What should the PMO professional do?


A.

Tell the project manager to refer to the organizational process assets (OPAs) for the change request template and provide support as needed.


B.

Instruct the project manager to follow the project management governance model, which has predefined processes and procedures for change requests.


C.

Support the project manager in creating the change request and guide the project manager through its submission and approval.


D.

Ensure that the project manager attends the required training that will provide more information about the change management process.


Get Premium PMI-PMOCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.