Question #: 24
Topic #: 3

The organization's PMO intends to transform its role into an agility-driven PMO.

Which option should the PMO leader take to help the PMO become more agile?


A.

Collaborate with PMO customers to develop and prioritize a comprehensive product backlog.


B.

Establish a process for collecting new ideas to improve PMO services for customers.


C.

Implement the Scrum framework within the agile teams to enhance collaboration.


D.

Introduce a collaborative software platform to streamline team communication.