PMI-PMOCP Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

During executive meetings, the leader of a recently established PMO notices that the organization ' s leaders are worried about falling revenues during the last quarter and are beginning to look for ways to cut costs. The PMO leader is concerned that the PMO may be cut.

What should the PMO do to mitigate this risk?


A.

Continue to demonstrate the value of the PMO.


B.

Increase the PMO ' s value by increasing the services provided by the PMO.


C.

Demonstrate alignment with the organization by reducing the PMO headcount.


D.

Improve the maturity of the PMO services.