In a large energy company, a PMO was recently established to help organize the numerous projects that are completed every year. Executives have passionate discussions in meetings to select and prioritize projects to enter the portfolio. These discussions cause frequent delays and result in decisions being questioned by some of the executive board members.

What should the PMO professional do to improve this situation?


A.

Facilitate the selection and prioritization process based on their own project management experience.


B.

Implement a portfolio management service that includes established criteria for project selection and prioritization.


C.

Ask the executives to discuss issues based on the projects' proposed business cases so that discussions are more objective.


D.

Suggest informal activities to build interpersonal relationships among the company executives.