PMI Project Management Office Certified Professional PMI-PMOCP Question # 17 Topic 2 Discussion

PMI Project Management Office Certified Professional PMI-PMOCP Question # 17 Topic 2 Discussion

PMI-PMOCP Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

The project sponsor and the manufacturing director of a PMO-managed project have different opinions about the development of a new order-tracking system.

What should the PMO professional do to avoid this situation in the future?


A.

Develop an effective project scope and change control process during project planning.


B.

Involve key stakeholders to ensure that requirements are not overlooked.


C.

Advise executives to complete a roles and responsibility matrix in the project planning.


D.

Ensure that the project sponsor has approved the requirements.


Get Premium PMI-PMOCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.