PMI Project Management Office Certified Professional PMI-PMOCP Question # 18 Topic 2 Discussion

PMI Project Management Office Certified Professional PMI-PMOCP Question # 18 Topic 2 Discussion

PMI-PMOCP Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

A mature enterprise PMO unit in a large, diversified holding is now supporting a new business unit as a result of an organizational transformation. The director of this unit expresses doubts on the value and benefits of PMO support during the annual budgeting process.

How should the PMO professional articulate the PMO's value and get buy-in from this stakeholder for the PMO services?


A.

Build the relationship from the bottom up by inviting middle management of the new business to an internal PMO event.


B.

Understand the director's doubts and extend an invitation to present project case studies and PMO success stories.


C.

Ask existing PMO accounts to provide the director with short video testimonials highlighting how they like the PMO.


D.

Involve the PMO sponsor in the next budgeting session to reinforce the PMO's position.