PMI-PMOCP Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

During the last portfolio steering meeting, business representatives complained about the sudden unavailability of some critical resources for a project with very high visibility and importance. The PMO leader was not informed of this risk by the project manager.

Which action should the PMO leader take to avoid similar situations in the future?


A.

Review the processes identified as critical with the project managers.


B.

Schedule regular meetings with all of the project managers.


C.

Identify the skills the project managers need additional training in.


D.

Facilitate the adoption of risk management practices by project managers.