PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 17 Topic 2 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 17 Topic 2 Discussion

PMI-ACP Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?


A.

Calculated planned percent complete (PPC)


B.

Many small minimally marketable features (MMFs)


C.

Story points rather than cost estimates


D.

Calculated earned value (EV)


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.