PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 138 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 138 Topic 14 Discussion

PMI-ACP Exam Topic 14 Question 138 Discussion:
Question #: 138
Topic #: 14

Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.

What should the Scrum Master do next?


A.

Alert the team that sprint goals might not be met and create an alternative plan


B.

Obtain team buy-in to perform modifications to the sprint backlog


C.

Have the sprint proceed as planned


D.

Ask the team to decide if the task should be reassigned


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.