Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date. What should the agile practitioner do?
A.
Deal with the issues in a retrospective if they ever come up again.
B.
Create a task board to track issues when they appear.
C.
Identify and monitor issues through a risk burndown chart.
D.
Create an issue log as an information radiator and monitor.