PMI-200 Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

An agile team is planning the next iteration for a product release that has accumulated technical debt What should the team do?


A.

Add code cleanup activities to the product backlog and request prioritization by the product owner


B.

Add code cleanup activities to the next iteration and request clarification from the product owner


C.

Add code cleanup activities to the next iteration and ask the product owner to end the current iteration


D.

Add code cleanup activities to the next release backlog and request documentation from the product owner