PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 120 Topic 13 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 120 Topic 13 Discussion

PMI-200 Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

What should the agile practitioner know about tracking velocity?


A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.


B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.


C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.


D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.