PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 119 Topic 12 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 119 Topic 12 Discussion

PMI-200 Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

Two similar stories A and B are estimated at 3 story points. Story C, is estimated at 8 points After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?


A.

Assign story B more than 8 story points so to provide a better estimate


B.

Add points to story B's iteration to account for the error but keep story B at 3 points


C.

Assign more resources to story B to bring it in line with the estimate


D.

Reestimate all stories including values for A; B and C


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.