Two similar stories A and B are estimated at 3 story points. Story C, is estimated at 8 points After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?
A.
Assign story B more than 8 story points so to provide a better estimate
B.
Add points to story B's iteration to account for the error but keep story B at 3 points
C.
Assign more resources to story B to bring it in line with the estimate
D.
Reestimate all stories including values for A; B and C
Chosen Answer: