PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 117 Topic 12 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 117 Topic 12 Discussion

PMI-200 Exam Topic 12 Question 117 Discussion:
Question #: 117
Topic #: 12

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release.

What should the agile coach do?


A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track


B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins


C.

In the upcoming retrospective, discuss ways to improve sharing project status information


D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date