PMI-200 Exam Topic 12 Question 116 Discussion:
Question #: 116
Topic #: 12

A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?


A.

Discuss the issue to reduce the backlog based on decreased productivity of the team.


B.

Collect updates from each team member before the meeting and share them with all members.


C.

Ask the team member to update daily progress on the information radiators.


D.

Change the team velocity to show positive progress in shared information radiators.