PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 110 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 110 Topic 12 Discussion

PMI-100 Exam Topic 12 Question 110 Discussion:
Question #: 110
Topic #: 12

Which tool or technique is an examination of industry and specific vendor capabilities?


A.

Independent estimates


B.

Market research


C.

Analytical techniques


D.

Bidder conferences