PMI-100 Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

Which document defines how a project is executed, monitored and controlled, and closed?


A.

Strategic plan


B.

Project charter


C.

Project management plan


D.

Service level agreement