PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 111 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 111 Topic 12 Discussion

PMI-100 Exam Topic 12 Question 111 Discussion:
Question #: 111
Topic #: 12

Which Control Quality tool is also known as an arrow diagram?


A.

Matrix diagram


B.

Affinity diagram


C.

Tree diagram


D.

Activity network diagram