PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 98 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 98 Topic 10 Discussion

PMI-100 Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?


A.

Monitor and Control Project Work


B.

Perform Quality Assurance


C.

Close Project or Phase


D.

Control Scope