New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 99 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 99 Topic 10 Discussion

PMI-100 Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

In the Plan Stakeholder Management process, expert judgment is used to:


A.

Provide information needed to plan appropriate ways to engage project stakeholders.


B.

Ensure comprehensive identification and listing of new stakeholders.


C.

Analyze the information needed to develop the project scope statement.


D.

Decide the level of engagement of the stakeholders at each required stage.


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.