PMI-100 Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

In the Plan Stakeholder Management process, expert judgment is used to:


A.

Provide information needed to plan appropriate ways to engage project stakeholders.


B.

Ensure comprehensive identification and listing of new stakeholders.


C.

Analyze the information needed to develop the project scope statement.


D.

Decide the level of engagement of the stakeholders at each required stage.