PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 97 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 97 Topic 10 Discussion

PMI-100 Exam Topic 10 Question 97 Discussion:
Question #: 97
Topic #: 10

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?


A.

Work performance data


B.

Project documents


C.

Scope baseline


D.

Requirements documentation


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.