PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 89 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 89 Topic 9 Discussion

PMI-002 Exam Topic 9 Question 89 Discussion:
Question #: 89
Topic #: 9

Which of the following is an output of a Verify Scope process?


A.

Accepted deliverables


B.

Change Requests


C.

Project document updates.


D.

All of the above


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.