PMI-002 Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

In which type of organization, a project manager is in complete control of the project?


A.

Projectized organization


B.

Balanced Matrix organization


C.

Strong Matrix


D.

Weak Matrix organization