PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 79 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 79 Topic 8 Discussion

PMI-002 Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

Estimated at Completion is determined by ___________.


A.

ETC + ACWP


B.

BAC - ETC


C.

BAC/CPI


D.

Both A and C