PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 77 Topic 8 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 77 Topic 8 Discussion

PMI-002 Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

When a risk should be avoided?


A.

The risk event has a low probability of occurrence and low impact.


B.

The risk event is unacceptable - generally one with a very high probability of occurrence and high impact.


C.

The risk can be transferred by purchasing insurance.


D.

A risk event can never be avoided.


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.