PMI-002 Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards is called __________.


A.

Quality Assurance


B.

Quality Control


C.

Plan Quality


D.

Quality Review