PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 53 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 53 Topic 6 Discussion

PMI-002 Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

On a project, quality should generally be of ________.


A.

Equal priority with schedule, but higher priority than cost


B.

Higher priority than cost and schedule


C.

Equal priority with cost, but higher priority than schedule


D.

Equal priority with cost and schedule


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.