PMI-002 Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

Decomposition is ___________.


A.

What happens when changes to the project scope are ignore


B.

Subdividing the major project deliverables into smaller, more manageable components


C.

Defining a general product description into more discrete definitions of individual components


D.

Subdividing the project into logical divisions of effort aligned within the performing organization's functional areas