PMI-002 Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

Projects are typically authorized as a result of any of the following except:


A.

Market demand


B.

Successful RFP bidding


C.

Regulatory requirement


D.

Technological advance