PMI-002 Exam Topic 21 Question 205 Discussion:
Question #: 205
Topic #: 21

The Person primarily responsible for the quality of deliverables is the.


A.

Quality control inspector.


B.

Project manager.


C.

Design engineer.


D.

Quality manager.