PMI-002 Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?


A.

Schedule


B.

Assumption


C.

Constraint


D.

Planning process