PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 165 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 165 Topic 17 Discussion

PMI-002 Exam Topic 17 Question 165 Discussion:
Question #: 165
Topic #: 17

A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $150,000 with a predetermined fee of $15,000 and a share ratio of 80/20. The actual cost of the project is $130,000. How much profit does the seller make?


A.

$31,000


B.

$19,000


C.

$15,000


D.

None of the above


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.