PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 153 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 153 Topic 16 Discussion

PMI-002 Exam Topic 16 Question 153 Discussion:
Question #: 153
Topic #: 16

A contingency plan is executed when _____________.


A.

A risks is identified


B.

An identified risk occurs


C.

When a workaround is needed


D.

Al1 of the above


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.