PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 111 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 111 Topic 12 Discussion

PMI-002 Exam Topic 12 Question 111 Discussion:
Question #: 111
Topic #: 12

A Reserve Analysis involves:


A.

Estimating by multiplying the quantity of work by productivity rate


B.

Adding resource reserves to the activity resource estimates


C.

Developing project schedule with contingency reserves as a recognition of the schedule risk


D.

Incorporating time buffers into the activity duration estimates


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.