PMI-002 Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

Inputs of Develop Project Team include all EXCEPT:


A.

Project staff


B.

Reward and recognition systems


C.

Resource calendars


D.

Project plan