Question #: 1
Topic #: 1

Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?


A.

Precedence Diagramming Method (PDM)


B.

Gantt Cnart Diagram (GCD)


C.

Dependency Diagramming Method (DDM)


D.

Arrow Diagramming Method (ADM)