PMI-001 Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

When cost variance is negative and schedule variance is positive, the project is:


A.

under budget and behind schedule.


B.

over budget and ahead of schedule.


C.

on schedule.


D.

complete; all planned values have been earned.