PMI-001 Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?


A.

Cost variance (CV)


B.

Cost performance index (CPI)


C.

Budget at completion (BAC)


D.

Variance at completion (VAC)