PMI Project Management Professional v5 PMI-001 Question # 131 Topic 14 Discussion

PMI Project Management Professional v5 PMI-001 Question # 131 Topic 14 Discussion

PMI-001 Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:


A.

Determine Budget.


B.

Baseline Budget.


C.

Control Costs.


D.

Estimate Costs.