PMI-001 Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

Which process involves identifying and documenting the logical relationships between project activities?


A.

Develop Schedule


B.

Sequence Activities


C.

Create WBS


D.

Applying leads and lags