CA0-001 Exam Topic 12 Question 118 Discussion
PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 118 Topic 12 Discussion
PMI Discussions
Browse All Questions
Go to Exam Detail
Get Premium Access
Previous
Next
PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 118 Topic 12 Discussion
CA0-001 Exam Topic 12 Question 118 Discussion:
Question #:
118
Topic #:
12
Who authorizes a project?
A.
Sponsor
B.
Project manager
C.
Project team
D.
Buyer
Show Answer
Get Premium CA0-001 Questions
Answer
Correct Answer:
A
Options Selected by Other Users:
Option A:
(98 votes)
89.91%
Option B:
(2 votes)
1.83%
Option C:
(5 votes)
4.59%
Option D:
(4 votes)
3.67%
Contribute your Thoughts:
Chosen Answer:
A
B
C
D
This is a voting comment
(
?
)
.
You can switch to a
simple comment
.
It is better to Upvote an existing comment if you don't have anything to add.
Maximum 400 character.
Submit
Awaiting moderator approval
Previous
Next
Modal title
×
Registered Required
×
In order to participate in the comments you need to be logged-in.
You can
sign-up
or
login
(it's free).
Submit