Question #: 117
Topic #: 12

What are the identified risks for doing excessive decomposition in a WBS?


A.

Insufficient project funding and disqualification of sellers


B.

Insufficient project funding and ineffective use of resources


C.

Disqualification of sellers and non-productive management efforts


D.

Non-productive management effort and inefficient use of resources