During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.


A.

Alternative identification


B.

"'s^ assessment


C.

Alternative selection


D.

Product analysis