Which statement is true about Bottom-up estimating?


A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.


B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.


C.

Using project characteristics (or parameters) in a mathematical model to predict costs.


D.

Cost of quality can also be used to prepare the schedule activity cost estimate.