The Programme Manager holds responsibility for ensuring that individual projects align with the overarching programme objectives during capability delivery. This role coordinates the interdependencies, monitors progress, and manages risks to ensure projects collectively deliver the intended outcomes.
The MSP Practitioner notes: “Programme manager is responsible for all tasks in delivering the capability. This is a continual activity throughout the programme.” This alignment ensures that outputs contribute directly to the transformational goals and benefit realization plan, avoiding scope creep or misaligned efforts.
While the Senior Responsible Owner (SRO) provides strategic accountability and the Business Change Manager (BCM) focuses on benefits realization, the Programme Manager operationalizes these objectives through effective project oversight and control.
The Programme Office supports through administrative and coordination activities but does not have direct accountability for strategic alignment of projects.
Maintaining this alignment is critical for delivering business value and achieving programme success in complex transformational environments.