New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Scrum Professional Scrum Master I PSM-I Question # 55 Topic 6 Discussion

Scrum Professional Scrum Master I PSM-I Question # 55 Topic 6 Discussion

PSM-I Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply.)


A.

Definition of “Done”.


B.

How the team does its work.


C.

Team relations.


D.

The value of work currently represented in the Product Backlog.


E.

Arranging the Sprint Backlog for the next Sprint.


Get Premium PSM-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.