PEGACPBA24V1 Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

An Assignment uses the following Service-Level Agreement: Initial Urgency: 5, Goal: 12 hours (increase Urgency by 10), Deadline: 24 hours (increase Urgency by 15), Passed Deadline: 4 hours (increase Urgency by 20, limit to 5 events). What is the Assignment Urgency 36 hours after the Case reaches the Assignment?


A.

70


B.

90


C.

50


D.

85