The PDCA (Plan-Do-Check-Act) model is a continuous improvement framework used in ISO 45001 and other management systems.
Plan: Establish objectives and processes to deliver results in line with the OH and S policy.
Do: Implement the processes.
Check: Monitor and measure processes against the policy, objectives, and requirements.
Act: Take actions to continually improve the system ' s performance.
Analysis of Options:
A. Plan, Do, Check, Act:Correct. This is the standard PDCA cycle.
B. Plan, Do, Check, Ask:Incorrect. " Ask " is not part of the cycle.
C. Plan, Deliver, Control, Achieve:Incorrect. This is not the PDCA cycle.
D. Prepare, Deliver, Control, Assess:Incorrect. This deviates from the PDCA framework.
ISO Reference:
Clause 0.3: PDCA model.
Submit